✔ Locate and move hardware to MDF/Computer or another area designated for staging
✔ Inspect hardware
✔ Install Fortigate (s)
✔ Install Fortiswitch(es)
✔ Install FortiExtender
✔ Turn up DIA/Broadband and LTE circuits
✔ Validate Circuit performance
✔ Label Patch Cables
✔ Identify critical endpoints within the store
✔ Provide Post-Site Photos of Work Area Clean and Free of Packaging/Debris
✔ Install the remaining switches / rackmount the switches that could not be rack mounted during visit 1
✔ Install the wireless Access Points (APs) ·
✔ Connect the switch patch cables, as per the switch remapping table ·
✔ Validate endpoint connectivity and application response